Mark IV Parkway construction continues

Posted March 14, 2017

Archived Content Information and links provided may no longer be accurate.

Storm system structures along the north side of Cantrell Sansom Road from Lionfish Way to Mark IV Parkway have been installed. Water line installations and fire hydrant relocations have been completed on the north side of the Mark IV Parkway and Cantrell Sansom intersection.

New school zone flashers will be activated within a few weeks.

A traffic switch occurred Feb. 15 that moved two-way traffic at the intersection back into the northbound travel lanes so final construction activities can be completed. Another traffic switch is slated for spring.

Construction is expected to be completed by the end of August 2017.

Get articles like this in your inbox weekly. Subscribe to City News

City News

Calendar

DFW International Airport Board of Directors: 8:30 a.m. June 29, 2017; Board Room - DFW Airport Headquarters Building, 2400 Aviation Drive.
View the agenda »

Foster Park Drainage & Erosion Control Project Meeting: 6 p.m. June 29, 2017; Southwest Regional Library, 4100 Library Lane.

Human Relations Commission: 5:30 p.m. July 3, 2017; Hazel Harvey Peace Center for Neighborhoods Room 201 AB, 818 Missouri Ave.
View the agenda »

View the full city calendar.