Panther Island bridges making progress

Posted Oct. 4, 2019

Archived Content Information and links provided may no longer be accurate.
construction
Steel reinforcement is being installed on the North Main bridge.

Significant progress continues on all three of the TxDOT signature bridges on Panther Island. Here are a few highlights:

Henderson Street Bridge

In late September, the contractor completed the final signature V-Pier on the Henderson Street Bridge. This means all 20 signature V-piers are now completed.

With all of the signature V-Piers complete, motorists can expect to see the superstructure false work (the temporary support structure for construction) to begin spanning this bridge. The superstructure false work is under construction on both the north and south ends of the bridge.

Once the superstructure false work is in place, the contractor will begin installing the steel reinforcement for the bridge’s box girder system. The box girder is the portion of the bridge that supports the roadway.

White Settlement Bridge

Work is well underway on the box girder superstructure on the White Settlement Bridge. The box girder is the portion of the bridge that supports the roadway. In August and September, the bridge contractor performed six major concrete pours associated with the bridge’s support system.

Major concrete pours have now been performed on three of the four bridge abutments. It is anticipated that four additional concrete pours will occur on the bridge in October.

North Main Bridge

The contractor has completed the superstructure false work for the North Main Bridge and is installing th steel reinforcement for the box girder systems over two of the signature v-piers. It is anticipated that the steel installation will continue into December.

The Panther Island project, which includes three signature bridges positioned along the to-be-realigned Trinity River, is a collaborative effort between the Trinity River Vision Authority, TxDOT, the City of Fort Worth, the North Central Texas Council of Governments, the U.S. Army Corps of Engineers and Tarrant County.

Get articles like this in your inbox. Subscribe to City News.

City News

Calendar

Grow With Google: Collaborate, Meet, and Work Remotely: 2 p.m. Aug. 12, 2020; Online.
Register for this event »

Collaborate, Meet & Work Remotely: 2 p.m. Aug. 12, 2020; Online.
Register for this event »

Southside Infrastruction Improvements Virtual Project Meeting: 6 p.m. Aug. 12, 2020; Virtual Meeting.

Fort Worth Human Relations Commission Mayor's Committee on Persons with Disabilities: 10 a.m. Aug. 13, 2020; WebEx.
View the agenda »
Register for this event »

Vendor Informational Forum for Minority and Women-Owned Business Enterprises: 11:30 a.m. Aug. 13, 2020; Fort Worth Business Assistance Center, 1150 South Freeway.
Register for this event »

Workforce Delivery Systems Committee: noon Aug. 13, 2020; Via Zoom.
View the agenda »

Regional Transportation Council Meeting: 1 p.m. Aug. 13, 2020; Teleconference meeting via Zoom.
View the agenda »

Community Action Partners (CAP) Council Special Called Meeting: 4 p.m. Aug. 13, 2020; WebEX.
View the agenda »
Register for this event »

West Risinger Road Improvements Virtual Project Meeting: 6 p.m. Aug. 13, 2020; Virtual Meeting.

City Council Workshop: 12:30 p.m. Aug. 14, 2020; City Council Conference Room 290, 2nd Floor, City Hall, 200 Texas St.
View the agenda »

City Council Work Session: 8:30 a.m. Aug. 18, 2020; City Council Conference Room 290, 2nd Floor, City Hall, 200 Texas St.

City Council Meeting: 10 a.m. Aug. 18, 2020; City Council Chambers, 2nd Floor, City Hall, 200 Texas St.

Notice of Public Hearing to consider amendments to the Trust Agreement for the Fort Worth Permanent Fund: 10 a.m. Aug. 18, 2020; City Council Chambers, 2nd Floor, City Hall, 200 Texas St.
View the agenda »

View the full city calendar and current meetings.