Capital Projects

Capital Projects

  • Roundabouts

Updates

I-35W Construction Closures and Detours

Construction on I-35W from I-30 to US 287 is in full swing. Capacity improvements span 18 miles and include a section of highway that is ranked as the state's eighth most congested roadway. Know the closures and detours before you get in the car.

Other Projects

Norwood Drive (Active through July 4, 2016)
Construction is scheduled for completion August 2016. Intersection and signal improvements are in the final stages on Trinity Boulevard. The utility pole at SH-10 was moved last week, which means the intersection improvements can proceed. These improvements will be made over the next six weeks.

Precinct Line Road from SH-10 to Concho Trail (Active through July 4, 2016)
Construction is 75 percent complete. Roadway closures are expected June 21 to June 30 so the contractor can do paving work. Bridge construction at Precinct Line Road and Trinity Boulevard will continue during the month of June. Project completion is scheduled for August 2016.

Trinity Boulevard Bridge & Drainage Improvements (Active through July 4, 2016)
The final phase of lane closures has traffic on the outside lanes allowing replacement of the median east of the bridge. After the rain stops and the median site dried out, an asphalt base can be placed. Construction on the median should last approximately 15 - 20 days. Traffic can then be restored to all four lanes. Project completion remains on schedule for June 2016.

Bond Projects

Visit the bond website to learn more about projects selected as part of the 2014 bond program.