10th Street Sidewalk & Bike Lanes

Project Description

This project will be constructed in two phases. Phase 1 will include sidewalk installation on the north side of 10th Street from Fournier Street to Forest Park and improvements to the pedestrian crossing at Forest Park and 10th Street that will provide a connection to the Trinity Trails.

Phase 2 of the project includes installation of a two-way cycle track for bikes from Penn Street to Forest Park.

Council District: District 9

Current Status: Construction

Project End Date: Oct. 31, 2017

Funding

Source: 2014 Bond Program Proposition 1
Amount: $143,044