Home > Capital Improvement Projects > Water and Wastewater Improvements

Big Fossil Creek Parallel Relief Sanitary Sewer Main M-402 Phase 2

Project Description

This is the final phase of a three phase plan of a single parallel sanitary sewer pipeline. The scope of work includes design of 8,800 linear feet of sanitary sewer pipeline, design survey, multiple junction structures, two wholesale customer meter stations and easement preparation. This is located along Big Fossil Creek from South of State Highway 121 to Broadway Avenue.

Council District: District 4

Current Status: Design

Project End Date: Jan. 28, 2020

Funding

Source: Water & Sewer Fund
Amount: $12,350,000

News

  • No updates available

Meetings

No meetings scheduled

Contact

Walter Norwood
817-392-5034