Bluebonnet Circle Infrastructure Improvements

Project Description

Existing water and wastewater lines will be replaced and the street will be reconstructed on Bluebonnet Circle.

Milestone Schedule University Drive approaches to be completed by Nov. 5, 2018.

All University Drive lanes opened by Nov. 8, 2018.

Interior sidewalks to be completed by Nov. 9, 2018

Pavement markings to be completed by Nov. 21, 2018.

Council District: District 9

Current Status: Construction

Project End Date: Nov. 21, 2018

Funding

Source: 2014 Bond Program Proposition 1
Amount: $3,860,097

Water and sewer improvements total $2.1 million and are funded from the Water & Sewer Fund. Street improvements in the amount of $674,500 are being funded from the 2014 Bond Program.