Project Description

This multi-phased project will address flooding in the Eastern Hills neighborhood in East Fort Worth.

Phase 1: A channel and multi-use detention basin / practice field for regional detention of stormwater was constructed in 2013.

Phase 2: Storm drain inlets were installed on Weiler Boulevard and Danciger Road. A spillway was constructed in an existing pond, and a channel was reconstructed downstream. This phase was completed during the Summer 2016.

Phase 3: Design is underway to install storm drains and inlets on Monterrey Drive and a portion of Jacqueline Road. Phase 3 is a joint effort with the Water Department and includes water, wastewater and pavement replacement.

Council District: District 4

Current Status: Design

Project End Date: Dec. 3, 2018

Funding

Source: Stormwater Capital Fund
Amount: $9,800,000