North Tarrant Express Water & Wastewater Line Relocations

From Loop 820 to I-30

Project Description

Fourteen pipe crossings for water and wastewater lines on I-35W, from Loop 820 to I-30, that are in conflict with the additional roadway lanes for the North Tarrant Express project will be relocated. The project will be done in four segments:

Segment 1: I-35W from Loop 820 to US 81/287 - Completed by March 2018

Segment 2: I-35W from Loop 820 to I-30 - Completed by December 2018

Segment 3: Loop 820 from Randol Mill Road to north of the interchange SH121/SH 183 - Completed by January 2023

Segment 4: I-35W from US 81/287 to Alliance Boulevard - TBD

Council District: District 2, District 4, District 8, District 9

Current Status: Construction

Project End Date: Jan. 20, 2023

Funding

Source: Water & Sewer Fund
Amount: $5,251,575

The funding for this project will come from the Texas Department of Transportation and the North Tarrant Express. The City of Fort Worth will contribute funds if a line size is increased in order to accommodate future growth.