Home > Capital Improvement Projects > Water and Wastewater Improvements

Randol Mill Road Wastewater Line Improvements

From Woodhaven Drive to Village Creek Wastewater Reclamation Facility

Project Description

This three-phase project replaces the major wastewater collection line from Woodhaven Drive to Village Creek Wastewater Reclamation Facility, and is part of a Sanitary Sewer Overflow Initiative agreement between the City of Fort Worth and the Texas Commission on Environmental Quality.

The first two phases are complete, and work is underway on the last phase.

The final phase is from an area west of Mallard Cove Subdivision along the Trinity River to Woodhaven Drive near Randol Mill Road. The existing wastewater line will be relocated from within Riverbend Estates into the right-of-way along Randol Mill Road. After this is complete, the existing line will no longer be used.

Wastewater line work within Riverbend Estates to connect the subdivision to the new section of the wastewater main is also part of the project. The existing 30-inch and 33-inch diameter line will be increased to a new 42-inch pipe. All lanes of Randol Mill Road are expected to be open to traffic by the end of February 2017.

The final phase of the Randol Mill Road Wastewater Line Improvement project should be complete by June 30, 2017.

Council District: District 4

Current Status: Construction

Project End Date: Sept. 29, 2017

Funding

Source: Water & Sewer Fund
Amount: $24,824,076

News

  • No updates available

Meetings

No meetings scheduled

Contact

Walter Norwood
817-392-5026