Capital Improvement Projects

Neighborhood Street Maintenance

The following neighborhood street maintenance projects use the following methods:

Joint Seal — Concrete pavement joints in the roadway will be cleaned and sealed.

Fog Seal — A fog seal (spray) application of a specially formulated asphalt emulsion will be applied to the existing asphalt roadway to prevent deterioration.

Micro-surfacing — A thin layer of asphalt emulsion seal-coat will be blended with finely crushed stone and applied to the roadway. This application will extend the life of the existing pavement.

Brick Rehab — Damaged brick in roadways will be removed and replaced.

Council District Street Status Type Estimated Completion
District 6 Camp Bowie Blvd
From Boland St. to Hulen St.
Construction Brick Rehabilitation June 30, 2019
District 7 Camp Bowie Blvd
From Hulen St. to Prevost St.
Construction Brick Rehabilitation June 30, 2019
District 9 Cherry St
From W 5th St. to W 10th St.
Construction Mill And Overlay June 5, 2019
District 9 E. 2nd St
From Main St. to Calhoun St.
Construction Brick Rehabilitation June 30, 2019
District 9 E. 8th St
From Commerce St. to Main St.
Construction Brick Rehabilitation June 30, 2019
District 9 Florence St
From W 7th St . to 100' N Of Lancaster Ave.
Construction Mill And Overlay May 31, 2019
District 9 Hemphill St
From W Oleander St. to W Boyce Ave.
Awaiting Start Date Asphalt Street Repair & Resurfacing January 1, 2020
District 9 Hemphill St
From W Vickery Blvd. to 430' N Of W Rosedale St.
Awaiting Start Date Asphalt Street Repair & Resurfacing January 1, 2020
District 9 Macon St
From Burnett St. to 200' N Of W 13th St.
Construction Mill And Overlay June 4, 2019
District 9 Main St.
From E Weatherford St to W 9th St.
Construction Brick Rehabilitation June 30, 2019
District 9 Monroe St
From W 13th St to 230' S Of W 13th St
Construction Mill And Overlay June 7, 2019
District 2 N Main St
From Pvmt Change to Pvmt Change Txdot
Construction Concrete Restoration May 31, 2019
District 9 N. Calhoun St.
From Weatherford St. to E. Belknap St.
Construction Brick Rehabilitation June 30, 2019
District 5 Rickenbacker Pl
From Carvely Dr. to Cass St.
Awaiting Start Date Concrete Restoration January 9, 2019
District 6 S Hulen St
From Columbus Trl. to W Cleburne Rd.
Awaiting Start Date Concrete Restoration April 26, 2019
District 3 S. Bellaire Dr
From S. Hulen St. to Arbarlawn Dr.
Awaiting Start Date Joint Seal June 3, 2019
District 6 Sycamore School Rd.
From Crowley Rd. to Mccart Ave.
Construction Joint Seal May 31, 2019
District 9 Taylor St
From W 10th St. to W Lancaster Ave.
Construction Mill And Overlay June 6, 2019
District 9 W 10th St
From Taylor St. to Henderson St.
Construction Mill And Overlay June 2, 2019
District 9 W 13th St
From Macon St. to Henderson St.
Construction Mill And Overlay June 3, 2019
District 9 W 13th St
From Jennings Ave. to Lamar St.
Construction Mill And Overlay June 1, 2019
District 9 W 13th St
From Throckmorton St. to Texas St.
Construction Mill And Overlay May 30, 2019
District 4 Western Center Blvd
From Bayberry Dr. to I-35w
Construction Concrete Restoration June 30, 2019

News

  • No news available

Meetings

Contact

Tariqul Islam
817-392-2486