Capital Improvement Projects

Neighborhood Street Maintenance

The following neighborhood street maintenance projects use the following methods:

Joint Seal — Concrete pavement joints in the roadway will be cleaned and sealed.

Fog Seal — A fog seal (spray) application of a specially formulated asphalt emulsion will be applied to the existing asphalt roadway to prevent deterioration.

Micro-surfacing — A thin layer of asphalt emulsion seal-coat will be blended with finely crushed stone and applied to the roadway. This application will extend the life of the existing pavement.

Brick Rehab — Damaged brick in roadways will be removed and replaced.

Council District Street Status Type Estimated Completion
District 6 Anewby Way
From W Cleburne Road to Channel View Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Arbor Gate
From Willow Way Road to Wind Chime Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Biloxi Drive
From Se Dead End to Misty Meadow Drive South
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Blue Grass Lane
From Misty Meadow Drive South to W Cleburne Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 4 Blue Water Lake Drive
From Park Vista Boulevard to Lawnsberry Drive
Construction In Progress Concrete Restoration Aug. 31, 2017
District 6 Bramblewood Road
From Misty Meadow Drive to Candlewind Lane
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Buttonwood Road
From Old Mill Run to Wind Chime Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Candlewind Lane
From Old Mill Run to Wind Chime Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Channel View Drive
From Church Park Drive to Weatherwood Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Church Park Drive
From W Cleburne Road to Blue Grass Lane
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Cooks Lane
From Ederville Road to Brentwood Stair Road
Construction In Progress Concrete Restoration Aug. 31, 2017
District 6 Foxfire Way
From Quail Hollow Road to Kingswood Drive
Construction In Progress Microsurfacing Sept. 29, 2017
District 6 Francisco Drive
From Kingswood Drive to French Lake Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 French Lake Drive
From Wind Chime Drive to Sleepy Ridge Circle
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Fuller Circle
From S Hulen Street to French Lake Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 4 Heritage Trace Parkway
From North Freeway to Ray White Road
Awaiting Start Date Concrete Restoration Change Dec. 30, 2017
District 6 Holly Spring Drive
From Misty Meadow Drive South to W Cleburne Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Hunters Glen Trail
From Racquet Club Drive to Racquet Club Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Kildee Lane
From Pheasant Walk Street to Wind Chime Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Kingswood Drive
From Wind Chime Drive to S Hulen Street
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Lemonwood Lane
From Misty Meadow Drive to Sycamore School Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Memphis Lane
From Misty Meadow Drive South to W Cleburne Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Newport Road
From Hunters Glen Trail to John T White Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Oak Crest Drive
From Nw Cul-De-Sac to Hunters Glen Trail
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Old Mill Run
From Arbor Gate to Sycamore School Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Perry Lane
From Francisco Drive to Fuller Circle
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Quail Hollow Road
From Willow Way Road to Quail Hollow Court
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Randol Mill Road
From Racquet Club Drive to John T White Road
Awaiting Start Date Concrete Restoration Sept. 29, 2017
District 5 Raquet Club Drive
From Randoll Mill Road to John T White Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Redfield Drive
From Kingswood Drive to Tall Meadow Lane
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 4 Rogue River Trail
From Blue Water Lake to N Cul-De-Sac
Awaiting Start Date Concrete Restoration Sept. 29, 2017
District 6 Santa Rita Drive
From Misty Meadow Drive South to W Cleburne Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Singleleaf Lane
From Woodway Drive to Misty Meadow Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 South Ridge Trail
From Misty Meadow Drive South to W Cleburne Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Sparrow Point
From Willow Way Road to Wind Chime Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Sugar Ridge Road
From Woodmoor Road to Woodacre Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Sylvan Drive
From Racquet Club Drive to John T White Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Tall Meadow Lane
From N Cul-De-Sac to S Hulen Street
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Teaberry Lane
From W Cleburne Road to Weatherwood Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 9 W Powell Avenue
From Hemphill Street to Lipscomb Street
Awaiting Start Date Concrete Restoration Sept. 29, 2017
District 5 Waterchase Circle
From Racquet Club Drive to Tennis View Court
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Waterchase Drive
From N Cul-De-Sac to Racquet Club Drive
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Weatherwood Court
From Sycamore School Road to S Cul-De-Sac
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Weatherwood Road
From Windhaven Road to Sycamore School Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Weatherwood Road
From Willow Way Road to Windhaven Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Wendover Drive
From Teaberry Lane to W Cleburne Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Wind Chime Drive
From Kingswood Drive to Sycamore School Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 6 Woodacre Road
From Misty Meadow Drive to W Cleburne Road
Awaiting Start Date Microsurfacing Sept. 29, 2017
District 5 Woodridge Drive
From Racquet Club Drive to Hunters Glen Trail
Awaiting Start Date Microsurfacing Sept. 29, 2017

News

  • No news available

Meetings

TCU Bicycle Lanes Project Meeting: 6 p.m. July 20, 2017; La Mancha Event Center, 3120 Merida.

Heritage Trace Concrete Restoration Project Meeting: 6 p.m. Aug. 10, 2017; Heritage Clubhouse, 9536 Courtwright Drive.

Gateway Area Infrastructure Project Meeting: 6 p.m. Sept. 13, 2017; Andrew "Doc" Session Community Center, 201 S. Sylvania Ave,.

Urban Drive & Northeast Parkway Street Construction Meeting: 6 p.m. Sept. 20, 2017; Diamond Hill Community Center, 1701 N.E. 36th St.

East Fort Worth Infrastructure Improvements Project Meeting: 6:30 p.m. Sept. 21, 2017; Handley United Methodist Church, 2929 Forest Ave.

Timberland Boulevard Improvements Project Meeting: 6:30 p.m. Oct. 3, 2017; Villages of Woodland Springs Amenities Center, 12209 Timberland Blvd.

East Rosedale Project Meeting: 6 p.m. Oct. 12, 2017; TCC Opportunity Center Room 1330, 5901 Fitzhugh Ave.

Allen Avenue Restriping Project Open House: 5:30 p.m. Oct. 18, 2017; Fire Station Community Center, 1601 Lipscomb St.

Diamond Hill Jarvis Infrastructure Improvements Project Meeting: 6 p.m. Oct. 25, 2017; Diamond Hill Community Center, 1701 Ne 36th St.

Lake Shore Area Street Rehabilitation Project Meeting: 6 p.m. Nov. 9, 2017; Tcc Opportunity Center, 1509 Fitzhugh Ave.

Contact

Tariqul Islam
817-392-2486