Upon submittal of complete permit application, the following review standards apply for first review comments.
Fire Code
Sign: 5 business days
Unified Sign Agreement Plan Review: 7-10 business days. Once all comments have been resolved, the agreement will be executed within 3 weeks
Plan Review: 7 business days
Inspections: Inspection requests received by 5 a.m. will be placed on that day's inspection list. Any inspections that didn’t get done, will be first on the following day’s list. Those received after 5 a.m. will be placed on the next day's list.
Administrative: 5 business days for first plan review comments. The entire contract agreement will be executed within 2-3 weeks
Council Approval: 6-8-week process. First review comments within 5 business days. Once all comments have been addressed, a Mayor and Council report will be drafted and routed for approval by the council