Playground Replacements

Closed October 27, 2022, 01:30 PM

  • Reference number102353
  • StatusOpen
  • SummaryThe major work will consist of the (approximate) following: the demolition and removal of 7 playgrounds at 7 different sites and the installation of 7 new playgrounds at each site. Other scope items include site grading, playground drainage, concrete flatwork and the installation of steps, ramps and handrails is also included in the scope of work.

Project Name: Playground Replacements at Arcadia Trail, Arcadia Trail South, Eugene McCray, Littlejohn, Marine, Quanah Parker, Wright-Tarlton Park 

Project No.: 102353

Dates of Bid Ad:  1st Ad on 10/06/2022, 2nd Ad on 10/13/2022

Pre- Bid Web Ex Meeting:  10/20/2022 at 1 P.M. CST

Bid Opening:  10/27/2022 at 2 P.M. CST

BIM 360 Bid Documents Public Shared Link:

 https://docs.b360.autodesk.com/shares/4cd32753-ce77-4775-8ae3-e8ca51c78f13