The major work will consist of the (approximate) following:
Constructing new water and sanitary sewer mains and paving.
Unit 1: Water Improvements
5623 LF – 8” PVC Water Pipe
6918 LF – Temporary Asphalt Paving Repair
81 EA – 1” Water Service
26 EA – 8” Gate Valve
Unit 2: Sanitary Sewer Improvements
3 EA – 4’ Manhole
200 LF – 8” Sewer Pipe
8 EA – Manhole Adjustment, Major w/ Cover
Unit 3: Paving Improvements
31660 SF – 4” Concrete Sidewalk
9643 SF – 6” Concrete Driveway
15040 SY – 6” Conc Pvmt
16125 SY – 8” Lime Treatment
500 SY – Pavement Pulverization (11”)
610 SY – 3” Asphalt Pvmt Type D
Unit 3: Paving Improvements Alternate A (POL)
13215 SY – 3” Asphalt Pvmt Type D
10128 LF – 6” Conc Curb and Gutter
13955 SY – Pavement Pulverization (11”)
Unit 4: Stormwater Improvements
143 LF – 21” RCP, Class III