Work to date including renovations, construction and updated decisions on dates:
- Management Forums were a success - over 250 attendees
- Council Chamber construction underway - mass timber beams set to be delivered in March of 2024
- First Council meeting is set to be winter of 2024-2025
- 12th and 20th floor construction is complete
- Mayor and council began occupying the space in January
- Floors 7 is next to be completed with move in scheduled for April
- Free Parking!
- Vertical garage expansions set to begin early 2024 and be completed Q3 of 2024
- Future City Hall Signage and Way finding Package is nearing completion
- Business Equity Spend is above goal
Prior to renovation and construction, the final scope for the program, including the four main elements of the program were decided:
- Tower Renovations to accommodate flexible floorplans the more than 23 City departments and 13 City buildings relocating to the tower
- Construction of a new council chambers facility on the site to accommodate the growing City of Fort Worth and better support the City’s Boards and Commissions
- Additional parking capacity to accommodate the more than 1400 City Staff and visitors coming to City Hall on a daily basis
- Development of a true municipal site, including additional sidewalk, gathering areas, and safety features