Current Impact Fees

The two tables below show the impact fees  that take effect on Jan. 1, 2022 and January 1, 2023. The City Council adopted the new fees on Sept.21, 2021 with ordinance number 25101-09-2021. View or download ordinance 25101-09-2021.

The 2023 costs remain in effect until the next study is completed and a new cost scheduled is adopted. State law requires impact fee studies be updated at least every five years.

Impact fees effective Jan. 1, 2022

The fees listed in the table below apply to plats recorded on or after April 1, 2017 with building permits issued on or after Jan. 1, 2022.

Meter Size Equivalency Factor Water Wastewater
5/8 inch x 5/8 inch 1 $1,870 $1,420
5/8 inch x 3/4 inch 1 $1,870  $1,420 
3/4 inch x 3/4 inch 1.5 $2,805  $2,130 
1 inch 2.5 $4,675 $3,550 
1-1/2 inch 5 $9,350 $7,100
2 inch 8 $14,960 $11,360
3 inch 21.75 $40,673 $30,885
4 inch 37.5 $70,125 $53,250
6 inch 80 $149,600 $113,600
8 inch 140 $261,800 $198,800
10 inch 210 $392,700 $298,200

 

Impact fees effective Jan. 1, 2023

The fees listed in the table below apply to plats recorded on or after April 1, 2017 with building permits issued on or after Jan. 1, 2023.

Meter Size Equivalency Factor Water Wastewater
5/8 inch x 5/8 inch 1 $1,981 $1,796
5/8 inch x 3/4 inch 1 $1,981  $1,796 
3/4 inch x 3/4 inch 1.5 $2,972  $2,694 
1 inch 2.5 $4,953  $4,490 
1-1/2 inch 5 $9,905  $8,980 
2 inch 8 $15,848  $14,368 
3 inch 21.75 $43,087  $39,063 
4 inch 37.5 $74,288 $67,350 
6 inch 80 $158,480 $143,680
8 inch 140 $277,340 $251,440
10 inch 210 $416,010 $377,160