This capital improvement program addresses needed street improvements by facilitating redevelopment and revitalization in identified areas of the Near Southside District.
Currently, TPW is proceeding with construction for Round Five of improvements. Rounds Six and Seven of proposed improvements are currently in design with plans to begin construction in 2026.
Improvements for Round Seven include replacing existing water and sewer lines in the identified streets, as well as rehabilitation of select portions of streets throughout Near Southside. Streets with proposed improvements for Round 7 include:
All street segments for this capital improvement program are located in Council District 9.
Design plans for the project are underway.
1714 South Henderson Street, Fort Worth 76110 View Map
1714 South Henderson Street , Fort Worth 76110
Design
2028