Culvert improvements are proposed for Comanche Trail between Malaga Drive and Marina Drive to address existing hazards from flood waters overtopping this location. In conjunction with the culvert improvements, the road will be widened and elevated to reduce the probability of flood waters flooding the roadway during high intensity rainfall events.
The project is located in District 7.
Construction of the new arch culvert, retaining walls and pavement have been completed. Traffic railing along the bridge and pavement markings will be installed in the coming weeks. The roadway should be opened to traffic in late January to mid-February.
7300 Comanche Trail, Fort Worth 761135 View Map
7300 Comanche Trail , Fort Worth 761135
Construction
February 2024
103396