East Northside Drive Bridge Replacement

  • Project typeStreet & Transportation Improvements
  • Project value$3,700,000
Street & Transportation Improvements

This project involves the full replacement of the bridge at East Northside Drive over Samuels Avenue, between Northpark Drive & Cold Springs Road.

New sidewalks will be installed along both sides of the bridge.

 

This project is in Council District 9 and borders Council District 2.

 

September 2024 Project Status

  • Demolition of the half section (west bound) of the bridge structure is completed.