Golden Triangle Boulevard

  • Project typeStreet & Transportation Improvements
  • Project value$10,000,000
Street & Transportation Improvements
  • A four-lane high-capacity road, also known as an arterial, will be constructed from I-35 to Misty Redwood Trail.
  • Proposed improvements include: 
  1. Traffic signals at Harmon Road and Golden Heights
  2. 10ft shared use path in each direction
  3. Drainage improvements
  4. Water line improvements

This project is in Council Districts 4 and 10.

 

July 2024 Project Update

The project design is near completion.

Right of way acquisition is complete.

Utility relocation is underway and expected to be completed in the Fall 2024.

Construction is set to begin early in 2025.

 

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • There is no project news available at this time.