The final Phase 4 of this project will involve the construction of storm drain lines, some sanitary sewer lines, and street repaving on Greenfield Road (east of Cindy Lane), Tee Head Drive, North Hill Road (Lea Crest Lane to Tee Head Drive) and ditch re-grading along Cindy Lane. Fort Worth Civil Constructors, LLC is the contractor on this project and will begin construction on June 5, 2023 with a planned ending date of June 4, 2024.
May 2023 Update
General Project Schedule
June & July 2023 – Cindy Lane grading from North Ridge to Greenfield Road
July & August 2023 –Greenfield Road storm drain construction from 6115 Greenfield to Cindy Lane
August thru December 2023 – North Ridge Road storm drain and sanitary sewer from Lea Crest to Tee Head Drive
December thru February 2024 – Tee Head Drive storm drain and sanitary sewer from North Ridge to Greenfield Road
February thru May 2024 – Greenfield Road storm drain and sanitary sewer from 6110 Greenfield Road east to the dead end
April thru May 2024 – Road paving starting on North Ridge Road then Tee Head Drive and finishing on Greenfield Road
This project is in Council District 2
5300 Cindy Lane, Fort Worth 76135 View Map
5300 Cindy Lane , Fort Worth 76135
Construction
February 2024
102975