Keller Hicks Road Improvements

  • Project typeStreet & Transportation Improvements
  • Project value$16,800,000
Street & Transportation Improvements
  • Project 100146 - Keller Hicks Phase 1 - Lauren Way to US 377  

Installation of a three-lane undivided concrete pavement section. Improvements to Keller Hicks and Katy intersection include:

  1. Left turn lanes
  2. Traffic signal
  3. Improved railroad crossing for cars and pedestrians 
  • Project 103276 (Phase 2) - Keller Hicks Phase 2 - Park Vista Blvd to Lauren Way

 Installation of a three-lane undivided concrete pavement section from Park Vista to Lauren Way.  Improvements include:

  1. Street lights
  2. 10' sidewalks  
  3. Traffic signal at Woodland Springs
  4. Storm water drainage

 

This project is in Council District 10.

 

June 2024 Project Update

  • Keller Hicks Phase 1 - Lauren Way to US 377  
  1. Contractor will be paving Keller Hicks between Katy and Lauren Way through end of June and begin work on Katy Intersection afterwards.
  2. Expect heavy road construction through the end of 2024.
  3. Please avoid construction zone and expect road closures and one way traffic.
  • Phase 2: 

Project is at 90% Design.

Right of Way Acquisition is Complete.

Utility Relocation has begun and will continue through 2024.

Road Construction to begin when Phase 1 is complete and Phase 2 Utility Relocation is complete in 2025.

Project meetings

Project news

  • There is no project news available at this time.

Location

100 Keller Hicks Road, Fort Worth 76244  View Map

Google Map