Lebow Channel Flood Mitigation

  • Project typeDrainage Improvements
  • Project value$90,000,000
  • Project schedulePhases over years
Drainage Improvements

The Lebow Channel area from Long Avenue north to DeRidder experiences regular flooding.  This project seeks to mitigate flooding from the channel by increasing the width and depth of the channel, improving each roadway crossing and providing a detention pond at Long Avenue.  The project will be implemented in phases over multiple years. 

 

The City has applied for State and Federal funding to help fund the projects.  It is anticipated to find our about these funding sources in the Fall of 2024.

 

This project is in Council District 2.

 

September 2024 Project Status

The City has applied for State and Federal funding to help fund the projects. It is anticipated to find out about these funding sources in the Fall of 2024.

 

Project meetings

Project news

  • There is no project news available at this time.

Location

1700 NE 37th Street, Fort Worth 76106  View Map

Google Map