This alignment study focuses on the proposed water transmission main that would extend from the Eagle Mountain Water Treatment Plant (6801 Bowman Roberts Road) at the southwest end, to the existing 36-inch in diameter Northside III water main at Willow Springs Road - at the Blue Mound Road West intersection - to the northeast.
This capital improvement project area is bound by:
This project is currently in two phases, but may be divided in to three phases with this study.
The southern part of the project is in Fort Worth Council District 7 and Fort Worth’s extraterritorial jurisdiction. The northern end is in Fort Worth Council District 10 and Fort Worth’s extraterritorial jurisdiction.
The proposed water transmission main will provide increased reliability for increasing and future growth in the far north area of Fort Worth.
The study will impact the Northwest Fort Worth neighborhood alliance.
US 287 Business at Bonds Ranch Road, Fort Worth 76179 View Map
US 287 Business at Bonds Ranch Road , Fort Worth 76179
Design
104940 Part 1
104940- Part 2
104940 Part 3
Part 1 - May 2028
Part 2 - November 2025
Part 3 - August 2027
104940
(PDF, 1013KB)map-northside-II-48-inch-water-transmission-main-alignment-and-land-study.pdf(PDF, 2MB)