Pharr Street Drainage

  • Project typeDrainage Improvements
Drainage Improvements

A cave has developed over a storm drain pipe and is in need of repair. TPW-Storm Water will have to investigate to see the extent of the problem and how many feet will need to be repaired.

 

 

This project is in Council District 9.

 

Project meetings

August 5, 2023 at 9:00 a.m.

Watch the August 5, 2023 Meeting

 

Project news

June 2023 Update 

  • The South Cravens bridge is closed until new construction is complete in 2024.  The bridge is closed due to safety concerns.  If you have concerns/questions, please email or call the project manager, Berton Guidry. 

Project Status

  • 60% Plans were submitted for Utility review
  • 75% Design PS&E were submitted June 23
  • 75% Flood Study in progress
  • 90% PS&E in progress, to be submitted July 21
  • Easement documents have been submitted for appraisals, which are due at the end of June
  • Scheduled to advertise for construction in September 2023

 