Seminary Hill Streets Project

  • Project typeStreet & Transportation Improvements
  • Project value$16,000,000
Street & Transportation Improvements

The proposed project provides for the design of water, sewer, and paving improvements on 13 neighborhood streets and 5 alleys.

  1. Boyce Ave, W -  E Dead end to McCart Ave
  2. Cherokee Trail - W Seminary Dr.   to W Gambrell St
  3. Gordon Ave - W Spurgeon St.  to S Dead End
  4. Martin Lydon Ave. - Townsend Dr.   to James Ave
  5. Rector Ave -W Seminary Dr, to W Gambrell St
  6. Yates St.  -W Dead End to James Ave
  7. Wayside Ave. - W Boyce Ave.   to Gambrell St.
  8. Cockrell Ave. - Seminary Dr.   to Morrell St. 
  9. Seminary Dr. - 155 ft. East of Rector Ave.   to 160 ft. West of Rector Ave
  10. Spurgeon St.-  Frazier Ave.   to Stanley Ave
  11. Stanley Ave.-  Martin Lydon Ave.   to   South Dead End
  12. Townsend Dr. - South Crest Dr.    to Yates St
  13. Frazier Ave. - Dead End/Spurgeon St.  to Pavement Change

 

This project is located in Council Districts 9 and 11.

 

March 2025 Project Status

  • Atmos Energy requires a line relocation to avoid conflicts with the project proposed Water and Sewer plans.
  • Consultant is working on submitting 100% Design Plans to reflect this.
  • Next, the Consultant will be working on advertising the project for bid.

 

Project meetings

  • There are no upcoming meetings at this time.

Project news

  • There is no project news available at this time.

 

Location

3208 w seminary drive, Fort Worth 76133  View Map