This project involves the total reconstruction of four streets in southeast Fort Worth. The following streets will be completely repaved. 

  • Burton Avenue - S. Hughes Avenue to the end of the road
  • Crouch Street - Burton Avenue to E. Berry Street
  • Quails Lane - Miller Avenue to S. Edgewood Terrace
  • Chickasaw Avenue - Miller Avenue to Martin Luther King Jr. Freeway

Project will now include utility and pavement work on Griggs Court from Quails Lane to Hatcher Street.

 

This project is located in Council Districts 5 and 11.

 

September 2024 Project Status

  • Contractor has started to work to install new water line at Griggs Court and will continue install over the coming month. 

Project meetings

  • View the February 2023 public meetings slides.

Project news

  • June 2023 Update: 

     

    Contractor is continuing work on Burton Avenue and Crouch Street installing utilities.  Utility work will continue through the end of June 2023, after which paving will begin starting in July 2023. 

    Utility work on Chickasaw is expected to commence in July 2023.

     