University Dr & BRIT Drainage project

  • Project typeDrainage Improvements
Drainage Improvements

This project involves the replacement of the entire drainage pipe to provide a better storm drain system.

The current pipe has several issues such as a hole on top and internal lining failures.

These will be addressed through full replacement of entire pipe and improved to current design standards.

 

 

This project is in Council District 7.

 

January 2025 Project Status 

Final Design Plans are almost complete. Beginning to coordinate a construction schedule with the contractor. 

 

 