The University Drive Phase 2 project proposes aesthetic improvements to the existing median and crosswalks.
A new six-foot sidewalk on the west side of University Drive from Trail Drive to Rock Springs Road is planned.
Crosswalk improvements and new traffic signals at the intersections of University Drive and Garden Blvd and Rock Springs Road.
This project also includes:
This project is in Council District 9.
Visit our University Drive Phase 1 page for additional information on University Drive improvements
The City will issue a Section 4f Notice in the Star-Telegram on Thursday, July 18, 2024, as required by federal regulations.
See the recent public meeting slides sharing the proposed design.
Summer 2024 Presentation(PDF, 1011KB)
Schedule Look Ahead:
Design Completion: Fall 2024
Bid & Award: Summer 2025
Construction: Summer 2026 – Summer 2027