Design and construction of safety and capacity improvements at the Basswood Boulevard crossing of the UPRR at the intersection of US 377 and at the Kroger Drive Crossing of the UPRR at the intersection of US 377. Improvements include roadway widening, construction of additional turn lanes, median, sidewalk, traffic signal and railroad gate/signal improvements.
This project is in Council District 4
Continue to coordinate with the UPRR to execute a Railroad Agreement necessary to move forward with the project.
Construction is anticipated to begin in October 2023
Construction is expected to be complete in March 2024
5650 Basswood Boulevard, Fort Worth 76137 View Map
5650 Basswood Boulevard , Fort Worth 76137