Westcliff Drainage Improvements

  • Project typeDrainage Improvements
  • Project value$14,200,000
Drainage Improvements

This is a multi-phase project to reduce flooding in the Westcliff and South Hills neighborhoods. Part of the project involves installing new larger pipes and strategically relocating other pipes that carry heavy rain water away from residents and streets.

 

Council Districts 3 and 9

 

May 2024 Project Status

Storm drain outfall construction and sewer construction on Anita Ave is completed.

In the coming weeks, the following work will be underway:

  1. Storm drain construction will continue along Suffolk Dr.
  2. Water pipe construction on Anita Ave.

 

 

.

 

 

Project news

  • September 11, 2023 

    New streets identified for work as part of the on-going water, sewer, and storm drain construction in the Westcliff Neighborhood. 

     

 