This is a multi-phase project to reduce flooding in the Westcliff and South Hills neighborhoods. Part of the project involves installing new larger pipes and strategically relocating other pipes that carry heavy rain water away from residents and streets.
This project is located in Council Districts 3 and 9.
Water work on Suffolk is completed.
Installation of the outfall began in February and will be completed by spring 2025.
Removal of previously installed blocked lines to be complete this month.
Concrete pavement repairs for Anita to be completed in April.
If you have any questions or concerns, please feel free to reach out to the Project Manager, Mike Bennett.
September 11, 2023
New streets identified for work as part of the on-going water, sewer, and storm drain construction in the Westcliff Neighborhood.
4300 clay ave, Fort Worth 76109 View Map
4300 clay ave , Fort Worth 76109
Phase 1: Construction
Phase 2: Construction
Summer 2025
Stormwater Capital Project Bonds Funds
C01669