Westcliff Drainage Improvements

  • Project typeDrainage Improvements
  • Project value$14,200,000
Drainage Improvements

This is a multi-phase project to reduce flooding in the Westcliff and South Hills neighborhoods. Part of the project involves installing new larger pipes and strategically relocating other pipes that carry heavy rain water away from residents and streets.

 

Council Districts 3 and 9

 

December  2024 Project Status

Right of way (R.O.W ) and easement acquisition are in progress.

Storm Drain Pipe Construction: This phase has been successfully completed.

Waterline Construction: Work has now begun on installing the new waterline.

Paving: Paving is scheduled to begin soon.

If you have any questions or concerns, please feel free to reach out to the Project Manager, Mike Bennett. You can contact him via email or phone.

 