Westcreek Channel Rehabilitation

  • Project typeDrainage Improvements
  • Project value$4,000,000
Drainage Improvements

This project includes maintenance work on the drainage channels Westcreek-Altamesa Channel (from Altamesa Boulevard to Westcreek Park) and McCart Channel (from McCart Avenue to Woodmont Park) to discuss . This work may include repairing the existing channel banks and stabilizing the channel.

June 2023 Update

The May 2023 meeting video is available on this site.

Project Details

Project Benefits

  • Mitigate Erosion
  • Maintain concrete paving and concrete toe

Anticipated Project Milestone Schedule (subject to change)

  • Complete design - October 2022
  • Bid & Award - Winter 2022
  • Construction start - Summer 2023
  • Construction complete - Winter 2024

 

Project is currently at 100% design

Easements and permits are being obtained

 

This project is in Council District 6 

Project meetings

Project news

  • There is no project news available at this time.

 

 

Location

6300 Westcreek Drive, Fort Worth 76133  View Map