Downtown Fort Worth Water and Sewer Main Replacements

  • Project typeWater and Wastewater Improvements
  • Project value$13,172,490.00
  • Contractor nameCircle C Construction
Water & Sanitary Sewer Imrpovements

This project will improve water service reliability by replacing old, large cast-iron water distribution mains and one sewer main.

Cast iron water main replacements:

  • West Lancaster Avenue from Florence Street to Summit Avenue
  • Summit Avenue from West Lancaster Avenue to West 5th Street
  • West 5th Street from Summit Avenue to Henderson Street
  • Henderson Street from West 5th Street to West 2nd Street 
  •  West 2nd Street from Henderson Street to Burnett Street
  • West 10th Street from Summit Avenue to Fournier Street
  • Easement through First Presbyterian Church park lot between Penn Street and Summit Avenue
  • Collier Street between West Lancaster Avenue and Texas Street
  • West 13th Street from Henderson Street to Florence Street
  • Florence Street from West Lancaster Avenue to West 13th Street

Sewer line replacement:

  • Summit Avenue between West Lancaster Avenue and Texas Street

The construction will occur in 12 phases. The streets in each phase are listed in the Project Phases section below.

  • Motorists will experience significant traffic impacts at various stages of construction.
  • The water utility and its contractor will work with businesses to ensure at least one point of access is always available.

  • Some businesses will be on a temporary water line during construction. Water meters are removed, and billing is based on historical usage data.

  • Visit this page regularly for updates on construction progress and street closures. Subscribe to receive updates using the link at the bottom of this page.

This project is in Fort Worth Council District 9. Construction will impact the Fort Worth Downtown Neighborhood Alliance. Landmarks include Trinity Terrace, First Presbyterian Church, First United Methodist Church, new City Hall, apartments and businesses

 

July 28, 2026 Update

  • The contractor anticipates resuming construction in late September or early October. The next phase of construction requires taking existing distribution lines out of service, which cannot be done during the peak summer demand period.
  •  When work resumes, the contractor will replace the cast-iron pipe in West Lancaster Avenue between Henderson and Collier streets.

Projected construction schedule

Current activity:

All construction is on hold until late September, when the peak summer water demand period ends. Construction will then resume in areas listed below.

  • Flush, disinfect and test new water line in Wet Lancaster Avenue. 
  • Replace existing cast-iron transmission main in West Lancaster Avenue between Henderson and Collier streets (westbound lanes).

  • Flush, disinfect and test new water line.

  • Road repairs for West Lancaster Avenue from Henderson Street to Summit Avenue will occur after above construction is complete.

 

 

Project Phases

The construction is divided into 12 phases. The work may not happen in the order of the phases.

Phase 1 (Complete)

  • Florence Street from West Lancaster Avenue to just north of West 13th Street
  • West 13th Street from westside of Henderson Street to just east of Florence Street

Phase 2 (in progress; work to resume in late September 2026)

  • West Lancaster Avenue from Florence Street to westside of Lake Avenue
  • Phase 2A: Installing a small-diameter water line in West Lancaster Avenue from Florence Street to Lake Street. (Complete)
  • Phase 2B: Replacing a large-diameter water line in West Lancaster Avenue from Florence Street to Lake Street.

Phase 3 (in progress; work to resume in late September 2026)

  • Installing a new large-diameter water line in West Lancaster Avenue from Lake Avenue to the west side of Summit Avenue 
  • Replacing an existing large-diameter water line in West Lancaster Avenue from Collier Street east to Lake Avenue (added to original project)
  • ADDED: Replace existing 30-inch cast iron water line in West Lancaster Avenue between Henderson and Collier streets. Decision is pending on whether work will begin in late July or wait until fall.

Phase 4 (estimated to begin Fall 2026) 

  • Summit Avenue from southside of West Lancaster Avenue to West 13th Street

Phase 5

  • Summit Avenue from West 13th Street to 10th Street

Phase 6 (complete)

  • Collier Street from Lancaster Avenue to just north of Texas Street

Phase 7

  • 10th Street from Fournier Street to Summit Avenue

Phase 8

  • Summit Avenue from 10th Street to West 5th Street

Phase 9

  • West 5th Street from west of Summit Avenue to West 2nd Street

Phase 10

  • West 5th Street from West 2nd Street to Henderson Street

Phase 11

  • Henderson Street from West 5th Street to West 2nd Street

Phase 12

  • West 2nd Street from Henderson Street to Burnet Street

Project Meetings

A community construction meeting was held on  Thursday, Feb. 27 at 9:30 a.m. concerning the replacement of large-diameter cast iron water mains that run through the western part of downtown Fort Worth, and, replacement of a sewer line in Summit Avenue.  Lancaster Avenue, and Collier Street). 

**A link to the recording of this meeting is found in the righthand column under Related Information.**

The water utility is offering to have smaller on-site meetings with businesses as construction approaches their location. Email wpe@fortworthtexas.gov if you are interested. Include the building name, address, contact name, contact's email and contact's phone number.

Location

Summit Avenue at West 10th Street, Fort Worth 76102  View Map

Google Map